| Rack standard | 19-inch EIA-310 |
| Installation | Horizontal |
| Height | 1U body section (44 mm) |
| Outlet configuration | 36× IEC C13 + 6× IEC C19 |
| Outlet rating | C13: 10 A; C19: 16 A |
| Input connection | Hard-wired terminal block, 5-wire |
| Input voltage | 380–415 V AC three-phase, 50/60 Hz |
| Max input current | 32 A per phase |
| Rated power | Up to 23 kW at 415 V |
| Phase | Three-phase |
| Main breaker | 3-pole breaker |
| Surge protection | None |
| Metering | LCD, current / voltage / power / energy per phase |
| Monitoring interface | RS485 Modbus-RTU |
| Outlet switching | None |
| Housing | Aluminium alloy, black anodised |
| Operating temperature | 10–45 °C |
| Relative humidity | 0–90% RH, non-condensing |
| Included accessories | M6×16 screws, user manual |
| Certification | CE / EMC / RoHS; built under ISO 9001 |
| Customisation | Outlet count, cord length and plug type to drawing |
| Lead time | 7–15 working days after drawing approval |
Datasheet, manual and drawings for this product (PDF).
Our engineers reply within 24 hours on business days.
Tel: +86-574-63783045
Email: ricky@idcpdu.com
Tell us your requirements — our sales team will get back to you with a quotation.
Yes, 36 C13 plus 6 C19 instead of 4. The difference is the inlet: three-phase 32 A raises capacity from 8 kW to 23 kW, which is the point of this model.
Spread the C13 banks so each phase carries about a third. Put switches and storage on different phases from the server banks, then check the per-phase current on the panel after the cabinet is populated.
A dense cabinet usually has a switch pair, a storage pair and a UPS outlet or PDU feed to accommodate. Six C19 positions avoid adapters on those cords.
Not on this build. If the site needs SPD, ask for a version with a 3-lamp module; the horizontal body can take it on the models with a deeper section.
A 32 A three-phase circuit with neutral and earth, protected by a breaker rated for the cable. The strip's own 3-pole breaker protects the strip and outlets, not the feed cable.